Title:
Centrifugal model test and numerical simulation on embankment with replacement of limestone soil
Author(s):
SUN Xiao1 ZHAO Ming-jie1 WANG Kui1 LONG Teng-hui2 YOU Hua-rong2
1. School of River and Ocean, Chongqing Jiaotong University, Chongqing 400074, China; 2. Chongqing Tongcheng Engineering Consultation Co Ltd, Chongqing 400023, China
Keywords:
road engineering high fill embankment centrifugal model numerical simulation
PACS:
U416.12
DOI:
-
Abstract:
The construction of test track has not ready criteria and rules in China, but it is a complex project, demanding higher construction technology and embankment settlement standard than expressway. Four typical sections of high fill embankment for Chang'an comprehensive test track were analyzed with centrifugal model test and numerical simulation to study the settlement deformation law of high fill embankment, and the settlement deformation of the sections that were replaced by limestone soil were analyzed. The results indicate that the strength and the stability of the high fill embankment are improved and the settlement deformation decreases when the high fill subgrade is replaced by limestone soil. The centrifugal model test results show a good agreement with numerical simulation results, and the settlement deformation and stability of the prototype can be reflected completely with combination of two methods.2 tabs, 6 figs, 16 refs.

References:

[1] 李运胜.论汽车试验场的建设与发展[J].公路交通科技,2000,17(6):5-9. LI Yun-sheng.Construction and development of proving ground[J].Journal of Highway and Transportation Research and Development,2000,17(6):5-9.(in Chinese)
[2]方红燕.对中国汽车试验场现状的思考[J].汽车工业研究,2009(6):33-36. FANG Hong-yan.The reflection of the present situation of automotive testing in China[J].Auto Industry Research,2009(6):33-36.(in Chinese)
[3]刘 宏,张倬元,韩文喜.高填方地基土工离心模型试验技术研究[J].地质科技情报,2005,24(1):103-106. LIU Hong,ZHANG Zhuo-yuan,HAN Wen-xi.Centrifugal model technique of high embankment[J].Geological Science and Technology Information,2005,24(1):103-106.( in Chinese)
[4]濮家骝.土工离心模型试验及其应用的发展趋势[J].岩土工程学报,1996,18(5):92-93. PU Jia-liu.The trend of the geotechnical centrifuge model test and its application [J].Chinese Journal of Geotechnical Engineering,1996,18(5):92-93.(in Chinese)
[5]赵明阶,王昌贤,杨锡武,等.公路岩堆路基沉降变形规律与施工控制深度研究[J].岩土工程学报,2010,32(1):33-40. ZHAO Ming-jie,WANG Chang-xian,YANG Xi-wu,et al.Settlement deformation properties and construction control depth of rock heap subgrade in highway[J].Chinese Journal of Geotechnical Engineering,2010,32(1):33-40.(in Chinese)
[6]张中云,蒋关鲁.客运专线无碴轨道红层泥岩改良土路基离心模型试验研究[J].铁道科学与工程学报,2010,7(5):41-46. ZHANG Zhong-yun,JIANG Guan-lu.Research on centrifugal model test of improved mudstone embankment for ballasted truck[J].Journal of Railway Science and Engineering,2010,7(5):41-46.(in Chinese)
[7]邹静蓉,杨 忠,郑国荣,等.土工格室加筋路堤边坡离心模型试验研究[J].公路工程,2007,32(5):5-9. ZOU Jing-rong,YANG Zhong,ZHENG Guo-rong,et al.Test research on centrifugal model of re-inforced geo-grid embankment slope [J].Highway Engineering,2007,32(5):5-9.(in Chinese)
[8]张 良,罗 强,陈 彪,等.基于离心模型试验的软基路堤基底压力和垫层筋带拉力分析[J].岩土力学,2010,31(9):2772-2779. ZHANG Liang,LUO Qiang,CHEN Biao,et al.Analysis of tensile force in reinforced cushion and pressure at bottom of soft soil foundation embankment based on centrifugal model tests[J].Rock and Soil Mechanics,2010,31(9):2772-2779.(in Chinese)
[9]黄茂松,李 波,程 岳.长短桩组合路堤桩荷载分担规律离心模型试验与数值模拟[J].岩石力学与工程学报,2010,29(12):2543-2550. HUANG Mao-song,LI Bo,CHENG Yue.Centrifugal model tests and numerical simulation of load sharing law for composite embankment with long and short piles[J].Chinese Journal of Rock Mechanics and Engineering,2010,29(12):2543-2550.(in Chinese)
[10]李士林,徐光明.单锚板桩结构码头离心模型试验研究[J].水利水运工程学报,2008(1):67-72. LI Shi-lin,XU Guang-ming.Centrifugal modeling tests for sheet-pile bulkhead anchored by single layer of tie-rods[J].Hydro-Science and Engineering,2008(1):67-72.(in Chinese)
[11]杜高昱, 何成建, 郝 飞. 高填方路堤施工工艺研究[J].筑路机械与施工机械化,2006,23(8):46-47,50. DU Gao-yu,HE Cheng-jian,HAO Fei. Research on construction technology of high fill embankment[J].Road Machinery & Construction Mechanization,2006,23(8):46-47,50.(in Chinese)
[12]王家全,周 健,丛 林,等.高填方加筋新旧路堤现场试验与数值模拟分析[J].岩石力学与工程学报,2009,29(增1):2943-2950. WANG Jia-quan,ZHOU Jian,CONG lin,et al.Analysis between numerical and field tests of high fill reinforced widening embankment[J].Chinese Journal of Rock Mechanics and Engineering,2009,29(S1):2943-2950.(in Chinese)
[13]单国峰,王曙光.高填方路堤施工沉降控制数值模拟分析[J].公路工程,2009,34(5):95-97. SHAN Guo-feng,WANG Shu-guang.Numerical simulation on construction settlement of high fill embankment [J].Highway Engineering,2009,34(5):95-97.(in Chinese)
[14]唐双林.高填石路堤施工及其稳定性监测技术[J].筑路机械与施工机械化,2009,26(2):43-45,49. TANG Shuang-lin.Construction and stability monitoring technology of high rock-filled embankment[J].Road Machinery & Construction Mechanization,2009,26(2):43-45,49.(in Chinese)
[15]孙 笑.长安综合试车场(垫江)高填方路基沉降变形和稳定性研究[D].重庆:重庆交通大学,2011. SUN Xiao.The study on the stability and settlement deformation of high fill subgrade for Chang'an comprehensive test track[D].Chonqqing:Chonqqing Jiaotong University,2011.
[16]孙 笑,赵明阶,汪 魁,等.长安综合试车场高填方路堤施工沉降控制数值模拟[J].重庆交通大学学报:自然科学版,2012,31(2):257-260. SUN Xiao,ZHAO Ming-jie WANG Kui et,al.Numerical simulation on settlement of Chang'an comprehensive test track with high fill embankment[J].Journal of Chongqing Jiaotong University:Natural Science,2012,31(2):257-260.(in Chinese)