|Table of Contents|

Optimization of construction of deep-buried long tunnel through faults

长安大学学报(自然科学版)[ISSN:1006-6977/CN:61-1281/TN]

Issue:
2011年06期
Page:
66-71
Research Field:
Publishing date:
2011-12-20

Info

Title:
Optimization of construction of deep-buried long tunnel through faults
Author(s):
LI Bing JIN Ai-bing WANG Yu DENG Fu-gen
School of Civil and Environment Engineering, University of Science and Technology Beijing, Beijing 100083, China
Keywords:
tunnel engineering fault deep-buried long tunnel center diagram method
PACS:
U455.4
DOI:
-
Abstract:
The construction of fault is used as project background in Zhangcheng highway tunnel, the dynamic excavation of tunnel is simulated in fault by means of FLAC3D, the center diagram method and bench cut method are adopted, and the mechanical response of the two methods are comparatively analyzed. The results show that the fault rock is mainly controlled by the maximum principal stress, the shear strain is mainly a trend of the center is smaller than both sides along the fault, both sides are smaller than the center along the vertical section, the right side is smaller than the left along the horizontal section. The surrounding rock mass are mainly shear failure, the upper wall is the most dangerous. In the context of this project, the center diagram method is better than bench cut method, the heading one is the key to center diagram method. 5 tabs, 6 figs, 14 refs.

References:

[1] 罗利锐,刘志刚.断层对隧道围岩稳定性的影响[J].地质力学学报,2009,15(3):226-232. LUO Li-rui,LIU Zhi-gang.Influenece of fault crush belts on the stability of tunnel rock[J].Journal of Geomechanics,2009,15(3):226-232.
[2]张 楠,王述红,王晓明,等.含弱层围岩的隧道变形破坏过程模型实验研究[J].地下空间与工程学报,2007,3(6):1085-1088. ZHANG Nan,WANG Shu-hong,WANG Xiao-ming,et al.Model study on mechanism of deformation and destruction of the surrounding rock in tunnel [J].Chinese Journal of Underground Space and Engineering,2007,3(6):1085-1088.
[3]方建勤,胡居义,林才奎,等.茶林顶隧道地应力演化及断层带施工力学分析[J].地下空间与工程学报,2009,5(3):536-539. FANG Jian-qin,HU Ju-yi, LIN Cai-kui,et al.Analysis on geo-stress evolution and construction mechanics of fault zone for Chalinding tunnel[J].Chinese Journal of Underground Space and Engineering,2009,5(3):536-539.
[4]廖秋林,侯哲生,何小东,等.断层影响下隧道围岩变形监测与特征分析[J].水文地质工程地质,2005(6):102-106. LIAO Qiu-lin,HOU Zhe-sheng,HE Xiao-dong,et al.Monitoring and analysis on the deformation of tunnel surrounding rock affected by faults[J].Hydrogeology and Engineering Geology,2005(6):102-106.
[5]李为腾,李术才,薛翊国,等.地质雷达在胶州湾海底隧道F4-5含水断层超前预报中的应用[J].山东大学学报:工学版,2009,39(4):65-68. LI Wei-teng,LI Shu-cai,XUE Yi-guo,et al.Application of ground penetrating radar to the geological forecast for water-bearing faults in the Jiaozhou bay sub-sea tunnel construction[J].Journal of Shandong University:Engineering Science,2009,39(4):65-68.
[6]罗利锐,刘志刚,陈文涛,等.红外探测技术在海底隧道地质预报中的应用[J].地下空间与工程学报,2010,6(4):775-780. LUO Li-rui,LIU Zhi-gang,CHEN Wen-tao,et al.Application of infrared acquisition technology in geological prediction of sub-sea tunnel[J].Chinese Journal of Underground Space and Engineering,2010,6(4):775-780.
[7]李天斌,孟陆波,朱 劲,等.隧道超前地质预报综合分析方法[J].岩石力学与工程学报,2009,28(12):2429-2436. LI Tian-bin,MENG Lu-bo,ZHU Jin,et al.Comprehensive analysis method for advanced forecast of geology in tunnels[J].Chinese Journal of Rock Mechanics and Engineering,2009,28(12):2429-2436.
[8]李 围.不同溶洞条件下公路隧道施工的关键技术[J].筑路机械与施工机械化,2010,27(10):68-71. LI Wei.Key technologies for construction of highway tunnel under different karst caverns[J].Road Machinery & Construction Mechanization,2010,27(10):68-71.
[9]陶 坤,李小龙,石红磊.长大管棚在隧道浅埋段的施工技术和质量控制[J].筑路机械与施工机械化,2010,27(10):65-69. TAO Kun, LI Xiao-long,SHI Hong-lei.Construction technology and quality control of big-long pipe-roof in shallowly buried section of tunnel[J].Road Machinery & Construction Mechanization,2010,27(10):65-69.
[10]龚建伍,夏才初,朱合华,等.鹤上大断面小净距隧道施工方案优化分析[J].岩土力学,2009,30(1):236-240. GONG Jian-wu,XIA Cai-chu,ZHU He-hua,et al.Optimal analysis of construction schemes for Heshang small-space tunnels with large section[J].Rock and Soil Mechanics,2009,30(1):236-240.
[11]张学言,闫澍旺.岩土塑性力学基础[M].2版.天津:天津大学出版社,2006.
[12]夏才初,龚建伍,唐 颖,等.大断面小净距公路隧道现场监测分析研究[J].岩石力学与工程学报,2007,26(1):44-50. XIA Cai-chu,GONG Jian-wu,TANG Ying,et al.Study on site monitoring of large-section highway tunnels with small clear spacing[J].Chinese Journal of Rock Mechanics and Engineering,2007,26(1):44-50.
[13]庄 宁,廖少明,孙忠成,等.大跨度小净距群洞隧道施工方案优化研究[J].地下空间与工程学报,2007,3(1):96-100. ZHUANG Ning,LIAO Shao-ming,SUN Zhong-cheng,et al.Optimization analysis of construction schemes for large span and small clear distance group tunnels[J].Chinese Journal of Underground Space and Engineering,2007,3(1):96-100.
[14]JTG D70—2004,公路隧道设计规范[S].

Memo

Memo:
-
Last Update: 2011-12-20